|
by [TC]² |
DAMA Final Report EXECUTIVE SUMMARY 2001 1 Introduction In order to accomplish DAMA's vision industry needed to become more focused on consumers by developing a supply chain management process that would be demand driven. To accomplish the vision meant supply had to be synchronized with demand. Production had to be synchronized to replenish product at the consumer's pull rate. In, 1994, the Project started by characterizing the supply chain. Then, focus groups with representation from all four sectors of the U.S. Softgoods Industry and the national laboratories further defined the primary needs for the project based on their vision for the future. The projected needs included: Collaborating across the entire supply chain This set the stage for DAMA to develop the tools and
methodology that would support collaborating and exchanging data across
the entire supply chain. It also meant developing an information system
infrastructure for sharing information selectively and securely across
the supply chain. The Internet was chosen as the vehicle for information
sharing in 1994. 2 Supply Chain Analysis A pair of men's wrinkle-free cotton slacks, From the product investigations, process step maps were developed for each of the four product pipelines, which included the fiber, textile, sewn products, and retail business processes. The process step diagrams displayed the activities necessary for the production of a product and serve as a tool for understanding where opportunities for improvement lie (See Figure 1).
The results of these pipeline investigations confirmed
the need for new tools and processes that address inter-enterprise supply
chain management and coordination. Management at this scale and complexity
cannot be accomplished through the use of company-focused decision support
tools that are necessarily limited in scope. Studies conducted under
the EM&S task revealed that inter-enterprise focused tools, also
called cooperative business management tools, are needed to achieve
true synchronization of the myriad manufacturing, transportation, and
business processes needed to manufacture softgoods and move them through
the supply chain to the consumer. 3 DAMA Supply Chain Architecture Through the work of the DAMA project, an inter-enterprise architecture has emerged. It was recognized that technology driven solutions were difficult to implement. Developing a solution for Demand Activated Manufacturing required more than a software program. Developing technology is relatively easy; developing technology that is used successfully is much more difficult. The most successful technical solutions must be business driven. The analysis of that concept led to a five-component architecture. DAMA's Inter-Enterprise Architecture (which spans multiple companies across a supply chain) is shown in Figure 3. Each company (enterprise) in a sector may have their own unique internal architecture for sharing corporate information. The key architecture for collaboration across the supply chain is the support of a common set of information available to all members of the supply chain. The information must be timely, accurate and secure.
The DAMA project has identified four distinct sectors (or tiers) of distributors and suppliers in the softgoods supply chain: retail, apparel, textile, and fiber. N-Tier is a term used to describe a supply chain with multiple tiers of suppliers. DAMA's early focus for developing an architecture to support demand activated manufacturing was technology-driven. In 1997, the DAMA leadership changed the focus to pursuing a top down or business-driven approach. This business-driven approach stressed the importance of understanding three fundamental concepts before the move to collaboration can be made: Knowledge of industry culture and business practices,
The activities described in the DAMA N-Tier Collaboration Model provide the logic for the Collaborative Industry Supply Chain Simulation (CISS) model. This model illustrates how a single demand plan is made visible to all members of the chain. It also shows how that information would be processed and shared with each company participating in the collaboration, as well as how the identification of exceptions and resulting collaboration to resolve those exceptions will occur.
Although the DAMA Architecture was developed based on sound concepts, it required validation to support the perceived benefits. In this effort, simulation models were developed to compare the performance of proposed collaborative supply chain solutions with the traditional supply chain operations. The measure of success is shown as improvements in lead-time and inventory levels. In order to validate the DAMA Architecture, multiple models were required to handle the various supply networks and business processes. The first of the models developed focused on accurately modeling the current supply chain and calculating lead times for the various partners in the supply chain. Subsequent models built on this framework and added functionality to support the DAMA Architecture that included the logic for collaboration between the supply chain partners. It resulted in a dramatic decrease in lead-time because it eliminated duplication of effort in many administrative departments and synchronized the flow of information. Once these models were developed, logic was added to determine inventory levels for each of the partners. The resulting two models include the lead-time calculations, as well as, the inventory levels at each stage of the supply chain. The results from the simulation models proved that the DAMA Architecture did, in fact, have a positive impact on order lead-time and inventory among the partners. The two lead times that were calculated for each Partner were the planning/production lead-time and the order lead-time. The planning/production lead-time is defined as the time when a forecast enters Demand Planning until a completed production order is sent to the Finished Goods Warehouse. The order lead-time is defined as the time from order receipt until it is delivered to customers. Model results are shown below and illustrated in Figure 5 and Figure 6: Across all partners in the collaborative supply
chain model (CISS), there was a reduction of 16 days in the order lead-time
versus the traditional supply chain model (TISS), which is a 49% decrease.
Also, the collaborative model reduced 137 days from the planning / production
cycle which represents a 49% decrease in time in the supply chain.
4 Conclusions and Observations The inability to accurately forecast what the consumer
would buy 6-12 months in the future, A number of important lessons were learned during DAMA. These lessons are not new in concept, but continue to arise in the research. And, even though the issues involved are understood conceptually, that does not imply they can be satisfactorily resolved in a short period of time. The lack of trust is a significant deterrent and is a universal problem. When companies do not trust one another, collaboration attempts fail. As a prerequisite, collaboration requires sharing more proprietary data than is currently shared. Another lesson learned was technology promotes change. Today, technology is not a showstopper for collaboration since there are many proprietary and commercial technologies available to support changes. With this new technology, an array of new business opportunities exists to support the change to collaboration and other new business paradigms. The DAMA Project concluded that demand activated manufacturing is the right answer. Demand activated manufacturing focuses on consumer demand throughout the supply chain and requires collaborative supply chain management. There are successful industry standard examples like Collaborative Planning, Forecasting, and Replenishment developed by the Voluntary Inter-industry Commerce Standards (VICS) group. Collaboration is implemented in three phases. The first phase is the preparation phase where business agreements define the scope, goals and roles of the supply chain partners. The second phase is the piloting phase where a small number of companies test the partnership procedures and technology to see if goals can be achieved. Then, when successful, the pilot is scaled up to the agreed upon operational level. Each phase should be accomplished in sequence. The entire process may take several years, depending on the company(s) and the industry. 5 Future Direction With the conclusion of the DAMA Project research by the industry and national laboratory teams, the intellectual property developed during the Project, has been turned over to the Textile Clothing Technology Corporation [TC]² and the DAMA Partners for use in the softgoods industry. Included in the intellectual property are available tools as listed in Section 8. It is the opinion of the DAMA Project that VICS, ATMI, and AAFA would all be excellent places to nurture the model as a possible standard or guidelines for future collaborative supply chain initiatives. DAMA participated in the work of three Voluntary Inter-industry Commerce Standards (VICS) group committees: 1) Internet Commerce Committee, 2) Collaborative Planning Forecasting and Replenishment (CPFR®), and 3) Collaborative Transportation Management (CTM). The VICS Internet Commerce Committee is chartered with evaluating and recommending Internet standards to the VICS membership. The VICS CPFR® group promotes collaborative forecasting between retailers and suppliers. DAMA helped the VICS CPFR® committee with concepts of joint business planning and participated on the CPFR® advisory committee. The primary focus was on business processes and data sharing. It is the expectation of the N-Tier CPFR® Committee
that the DAMA N-Tier Collaboration Model work will be an entry point
for mapping the general model to specific industry N-Tier models. [TC]²
will continue to collaborate with VICS and incorporate some of the DAMA
technologies, methodologies, and concepts into industry standards. |